PROJECT BLV02

Multipurpose buoy laying vessel


Purpose:

  1. control of a condition of a fairway over internal waterways and water areas of ports;
  2. control of a condition of a navigating protection of a fairway, the control of burning of fires over signs on shined conditions;
  3. arrangement and removal of signs, and also their moving at change of borders of a fairway;
  4. service of signs on navigable conditions and repair of the light-signal equipment.

# Name Value
1. Main dimension
Length overall, m 43.09
Length between PP, m 37.90
Breadth overall, m 10.20
Breadth on DWL, m 9.20
Depth at midship, m 3.30
Air draft at draught d = 2.50, m 10.80
L x B x H 43.09 x 10.20 x 3.30 = 1450
2. Draught on DWL, m 2.50
3. Deadweight at draught d = 2.50 m, t 266
4. Endurance, days 7
5. Hold capacity, m³ 96
6. Oil recovery tank capacity, m³ 56
7. Bollard pull, t 10
8. Lifting capacity of bow cargo crane 8.0 t with boom 10 m
9. Lifting capacity of stern cargo crane 0.85 t with boom 6.5 m
10. RS class KM ° Ice3 R2-RSN AUT3-C
11. ME power, kW 2 x 405
12. Rudder and propeller complex 2 x Rudderpropellers
13. Auxiliary diesel-generators, kW 2 x 130
14. Hot water boiler, kW 81.4
15. Crew / special stuff, pers. 8 / 4
16. Speed, knots 10.0